Re: SAP PM scheduling problem

$
0
0

Hello

 

If you would like to have new planned dates if your work order completed early or late.Please go for Restart Option of Maintenance Plan IP10. Pop will come with below option

 

Delete - is the standard processing option

Skip - if you need the history

 

So select the Option DELETE

 

Then it will ask you to fill in New Start of Cycle so Please select date on which your Last Call (Work order) is completed it will give new planned date as per your cycle length.e.g.

2nd Order : 29th November

3rd Order ; 29th December

 

Please before carrying out above activity select  the radio button in scheduling Indicator as TIME in TC IP02.

 

Br

Rakesh