If you would like to have new planned dates if your work order completed early or late.Please go for Restart Option of Maintenance Plan IP10. Pop will come with below option
Delete - is the standard processing option
Skip - if you need the history
So select the Option DELETE
Then it will ask you to fill in New Start of Cycle so Please select date on which your Last Call (Work order) is completed it will give new planned date as per your cycle length.e.g.
2nd Order : 29th November
3rd Order ; 29th December
Please before carrying out above activity select the radio button in scheduling Indicator as TIME in TC IP02.